Enter your project values on the left and click Calculate to see all EVM metrics instantly.
All EVM calculations follow the PMBOK standard. Here are the core formulas:
| Metric | Good | Warning | Bad |
|---|---|---|---|
| CPI | > 1.0 | 0.9–1.0 | < 0.9 |
| SPI | > 1.0 | 0.9–1.0 | < 0.9 |
| CV | Positive | Small negative | Large negative |
| SV | Positive | Small negative | Large negative |
| TCPI | < 1.0 | 1.0–1.1 | > 1.1 |
Earned Value Management (EVM) is a structured way to measure project performance. It connects three key data points: how much work was planned, how much work was actually done, and how much it cost to do it.
Originally developed for US government contracts in the 1960s, EVM is now part of the PMBOK Guide and is used by project managers in construction, IT, aerospace, and many other industries worldwide.
The core idea is simple: comparing what you planned to spend with what you actually spent tells you how efficient you are — and lets you forecast whether the project will finish on time and within budget.
CPI (Cost Performance Index) tells you how much value you are getting per unit of money spent. CPI = 1.0 means exactly on budget. CPI = 0.80 means you are getting only 80 cents of value for every dollar spent — meaning you will overspend unless performance improves.
SPI (Schedule Performance Index) tells you how efficiently the project is moving through planned work. SPI = 1.0 means exactly on schedule. SPI = 0.75 means you have only finished 75% of the work you should have by now.
Together, CPI and SPI give a clear picture of project health — and they feed directly into the EAC forecast for final cost.
There are four common ways to estimate the final project cost (EAC). Each suits different situations:
TCPI (To-Complete Performance Index) answers the question: "How efficiently must we use the remaining budget to hit our cost target?"
TCPI = (BAC − EV) ÷ (BAC − AC)
If TCPI = 1.0, you need to perform exactly as planned for the rest of the project. If TCPI = 1.2, you need to be 20% more efficient than you have been — which is often unrealistic. A TCPI above 1.1 is a warning sign that the budget target may not be achievable.
TCPI is one of the most overlooked but most important EVM metrics for project forecasting and recovery planning.
How much your final project cost changes depending on your CPI, for a $100,000 BAC project.
| CPI Value | Meaning | EAC (BAC ÷ CPI) | Overrun vs. BAC | Project Status |
|---|
Based on BAC = $100,000. EAC = BAC ÷ CPI. A CPI of 1.0 means on budget; below 1.0 means over budget.
What each SPI value means for a 12-month project timeline.
| SPI Value | Meaning | Work Done vs. Planned | Delay Estimate (12-mo project) | Status |
|---|
Delay estimate is approximate: Estimated Duration = Planned Duration ÷ SPI. Delays compound over time if SPI does not recover.
How each EAC formula produces a different final cost estimate on a $100,000 project at 50% complete.
| CPI | EAC (BAC÷CPI) | EAC (AC+remaining) | EAC (AC+remaining÷CPI) | EAC (÷CPI×SPI) SPI=0.9 |
|---|
BAC = $100,000. Assumes project is 50% complete (EV = $50,000). AC = EV ÷ CPI. SPI fixed at 0.9 for last column.
How hard the team needs to work to stay within budget, depending on how much has been spent vs. planned.
| % Complete | EV Achieved | AC (at CPI 0.85) | AC (at CPI 0.95) | TCPI to meet BAC (CPI 0.85) | TCPI to meet BAC (CPI 0.95) | Feasible? |
|---|
BAC = $100,000. TCPI > 1.1 is generally considered very difficult to achieve. TCPI > 1.2 is rarely feasible without significant scope reduction.
How EVM is applied across sectors and typical CPI/SPI thresholds teams aim for.
| Industry | EVM Usage | Typical CPI Target | Typical SPI Target | Common Standard | Key Challenge |
|---|---|---|---|---|---|
| 🏗️ Construction | Very common | 0.95–1.05 | 0.90–1.10 | AACE, PMI | Weather & material delays |
| 💻 IT / Software | Widely adopted | 0.90–1.05 | 0.85–1.10 | PMBOK, Agile EVM | Scope creep |
| ✈️ Aerospace & Defense | Mandatory (US DoD) | > 0.95 | > 0.95 | ANSI/EIA-748 | Complex integration |
| ⚗️ Pharma / R&D | Moderate | 0.88–1.05 | 0.85–1.05 | PMI, internal | Regulatory approvals |
| ⚡ Energy / Utilities | Common | 0.92–1.03 | 0.90–1.05 | PMI, ISO 21500 | Permitting |
| 🏛️ Government | Required (many countries) | > 0.95 | > 0.95 | OMB (US), OGC (UK) | Budget cycles |
| 🚢 Shipbuilding | Common | 0.92–1.02 | 0.88–1.05 | NAV-SEA, PMI | Long lead items |
| 🏥 Healthcare | Growing | 0.90–1.05 | 0.88–1.05 | PMI, PRINCE2 | Stakeholder alignment |
Ranges are typical industry benchmarks and may vary by organization, project size, and contract type. Always validate against your organization's own tolerance thresholds.